Heartbeat #5
From: Team #3 (Dalat, Chris, Shadi, Fritz, and Tyler)
Heartbeat Msg: #5
To: ECE470/CSC402 Instructors
To email: net_heartbeat@renoir.csc.ncsu.edu
Subject: Heartbeat #5 from Team 3
Date: 9/27/02
1. Task Status:
- Continue updating web pages.
- Worked on and finished Homework #3.
- Started to read RFCs and product specs for the project
- Created a rough schedule of milestones for the semester.
- Setup a meeting time with our mentor on Thursday October 10, at 9am.
- Our first presentation on the project has been given.
Below is the schedule file:
[Schedule]
2. Personnel Status:
Dalat Bui - Lead,
Chris Brezovec - Vice Lead
K. Fritz Lehr - Webmaster
Shadi Eskama - Member
Tyler Humprey - Member
3. Risk Status:
- Heartbeat #4 was not adequate because of the use of absolute paths which
broke the links. Need to verify all links on the web work.
- Homework #4 is due next Thursday. This may require our group to
be rushed due to the quick turnaround time.
4. Problem List:
- Our project requires a lot of reading to get up to speed, and this may
be a problem for some people to get done in time..
- Some pages on the team website still need to be fixed. For example,
some pages need to have broken links finished and the project name added
to them.
5. Any other issues you wish to report, raise, address, ...
None at this time.
End-of-Msg
|