Team 3 Schedule
   
    Chris Dalat Fritz Shadi Tyler  
Task ID Tasks Planned Start Planned End Actual Start Actual End Hrs per week Hrs per week Hrs per week Hrs per week Hrs per week  
 
1 Organize team 13-Sep-02 13-Sep-02 13-Sep-02 13-Sep-02 X X X X X  
2 Install server 14-Sep-02 14-Sep-02 14-Sep-02 14-Sep-02 X X X X X  
3 Server configuration 16-Sep-02 16-Sep-02 16-Sep-02 17-Sep-02 X X X X X  
4 Design Website 17-Sep-02 17-Sep-02 17-Sep-02 17-Sep-02 X X X X X  
5 Inventory Link 24-Sep-02 24-Sep-02 24-Sep-02 25-Sep-02 X X X X X  
6 Meet with J. Streck 26-Sep-02 26-Sep-02 26-Sep-02 26-Sep-02 X X X X X  
7 Presentation Preparation 29-Sep-02 30-Sep-02 29-Sep-02 1-Oct-02 X X X X X  
8 Test #3: Group Presentation 1-Oct-02 1-Oct-02 1-Oct-02 1-Oct-02 X X X X X  
9 HomeWork #3 Due 4-Oct-02 4-Oct-02 30-Sep-02 4-Oct-02 X X X X X  
10 Read RFCs 30-Sep-02 9-Oct-02 30-Sep-02 24-Oct-02 X X X X X  
11 Meeting with Kumar (our mentor) 10-Oct-02 10-Oct-02 10-Oct-02 10-Oct-02 X X X X X  
12 HomeWork #4 - Part 1 Due 11-Oct-02 11-Oct-02 10-Oct-02 11-Oct-02 X X X X X  
13 Fall Break 12-Oct-02 15-Oct-02 12-Oct-02 15-Oct-02 X X X X X  
14 HomeWork #4 - Part 2 Due 17-Oct-02 17-Oct-02 17-Oct-02 17-Oct-02 X X X X X  
15 Read Specs for different brands 30-Sep-02 19-Oct-02 30-Sep-02 24-Oct-02 X X X X X  
16 Meeting with Kumar 24-Oct-02 24-Oct-02 24-Oct-02 24-Oct-02 X X X X X  
17 HomeWork #5 Due 24-Oct-02 24-Oct-02 24-Oct-02 24-Oct-02 X X X X X  
18 Firewall Certification 31-Oct-02 31-Oct-02     3 - - - -  
19 Write Algorithm for Testing Session Capacity 24-Oct-02 5-Nov-02     - - 5 - -  
A PPPoE 24-Oct-02 1-Nov-02     - - 4 - -  
B PPPoA 1-Nov-02 3-Nov-02     - - + - -  
C PPPoEoA 3-Nov-02 4-Nov-02     - - + - -  
D Rough Draft 4-Nov-02 5-Nov-02     - - + - -  
20 Write Algorithm for Testing Throughput 24-Oct-02 5-Nov-02     - - - 6 -  
A Packet Loss 24-Oct-02 1-Nov-02     - - - 4 -  
B Throughput 1-Nov-02 2-Nov-02     - - - + -  
C Latency 2-Nov-02 4-Nov-02     - - - + -  
D Rough Draft 4-Nov-02 5-Nov-02     - - - + -  
21 Write Algorithm for Testing Session Establishment Rate 24-Oct-02 5-Nov-02     - 4 - - -  
A Determine Max Rate 24-Oct-02 4-Nov-02     - 4 - - -  
B Rough Draft 4-Nov-02 5-Nov-02     - + - - -  
22 Write Algorithm for Testing Session Stability 24-Oct-02 5-Nov-02     2 - - - -  
A With Presence of Repeated Session Establishments 24-Oct-02 1-Nov-02     2 - - - -  
B With Presence of Repeated Session Teardowns 1-Nov-02 4-Nov-02     + - - - -  
C Rough Draft 4-Nov-02 5-Nov-02     + - - - -  
23 Write Algorithm for Testing Data Forwarding Stability 24-Oct-02 5-Nov-02     - - - - 5  
A With Presence of Repeated Session Establishments 24-Oct-02 1-Nov-02     - - - - 4  
B With Presence of Repeated Session Teardowns 1-Nov-02 4-Nov-02     - - - - +  
C Rough Draft 4-Nov-02 5-Nov-02     - - - - +  
24 Study for Test #4 27-Oct-02 28-Oct-02     10 10 10 10 10  
25 Test #4: Individual Test 29-Oct-02 29-Oct-02     1 1 1 1 1  
26 Learn How to Physically Use AC Devices (Lab) 30-Oct-02 6-Nov-02     1 1 1 1 1  
27 Meeting with Kumar (go over Rough Drafts) 7-Nov-02 7-Nov-02     + + + + +  
28 Individual Rough Draft Revisions 7-Nov-02 9-Nov-02     + + + + +  
29 Write Scripts to Test the AC Devices 8-Nov-02 15-Nov-02     + + + + +  
A Scripts for Part 1 8-Nov-02 15-Nov-02     + - + - -  
B Scripts for Part 2 8-Nov-02 15-Nov-02     - + - + +  
C Scripts for Part 3 8-Nov-02 15-Nov-02     - + - + +  
30 Test #5: In Lab Team Project Test 12-Nov-02 14-Nov-02     + + + + +  
31 HomeWork #6 Due 12-Nov-02 12-Nov-02     + + + + +  
32 Test Scripts on AC Devices 16-Nov-02 19-Nov-02     + + + + +  
33 Draft-Put-Together and Draft Revision 19-Nov-02 20-Nov-02     + + + + +  
34 HomeWork #7 Due 19-Nov-02 19-Nov-02     + + + + +  
35 Meeting with Kumar (Go Over Final Draft) 21-Nov-02 21-Nov-02     + + + + +  
36 RFC Completion 22-Nov-02 27-Nov-02     + + + + +  
37 Thanksgiving Break 28-Nov-02 1-Dec-02     + + + + +  
38 Presentation Preparation 2-Dec-02 4-Dec-02     + + + + +  
39 Test #6: Team Presentation & Demos 5-Dec-02 5-Dec-02     + + + + +  
40 Project Documentation 25-Nov-02 11-Dec-02     + + + + +  
A Part I WriteUp 25-Nov-02 6-Dec-02     + - - - -  
B Part II WriteUp 25-Nov-02 6-Dec-02     - + - - -  
C Part III WriteUp 25-Nov-02 6-Dec-02     - - + - -  
D Part IV WriteUp 25-Nov-02 6-Dec-02     - - - + -  
E Part V WriteUp 25-Nov-02 6-Dec-02     - - - - +  
F Parts-Put-Together and Revisions 6-Dec-02 12-Dec-02     + + + + +  
41 HomeWork #8 Due (Project Completion) 12-Dec-02 12-Dec-02     + + + + +  
42 Done with CSC402 / Party =) 13-Dec-02 13-Dec-02     + + + + +  
   
Color What it means   Member Name Role E-mail Phone  
  Deadline reached   Dalat Bui Lead dnbui@unity.ncsu.edu 851-3580  
  Overdue   Chris Brezovec Vice Lead crbrezov@unity.ncsu.edu 816-0349  
xxxxxx Sub-sections of other assignments   Fritz Lehr Webmaster kflehr@unity.ncsu.edu 605-8822  
xxxxxx Class Assignments   Shadi Seskama Member seskama@unity.ncsu.edu 593-0162  
xxxxxx Breaks   Tyler Humphrey Member tjhumphr@unity.ncsu.edu 601-5774  
xxxxxx Everything else            
     
+ Participated or Will Participate in the Task    
- Not involved with the task        
X Unknown    
   
   
   
This page was last updated on:  
Friday, November 01, 2002 17:41  
Copyright © 2002 by Team 3, All Rights Reserved.  
WebSite contact: K. Fritz Lehr, E-mail: kflehr@unity.ncsu.edu, Tel: (919) 593-0162